Variable Threshold Block Scenarios

Below are three scenarios that demonstrate use of the Demand-Based Minimum fields:

Example 1:

  • Charge the first 450 kWh per contract kW of billing demand at 0.0400 per kWh.
  • Charge all remaining consumption at 0.0353 per kWh.

The rows in the grid would be completed as follows:

Through Rate Demand Type Above Multiplier Other Amount
0 0.0400 Contract Demand 0 450 <blank>
999,999,999 0.0353 <blank> <blank> <blank> <blank>

 

Example 2:

  • Charge 0.12555 for the first 700 kWh. If the kW of billing demand is greater than 5 kW, add 150 for each additional kW.
  • Charge 0.08725 for the next 2500 kWh.
  • Charge 0.07125 for the additional kWh.

The rows in the grid would be completed as follows:

Through Rate Demand Type Above Multiplier Other Amount
700 0.12555 Billed Demand 5 150 <blank.
2500 0.08725 <blank> <blank> <blank> <blank>
999,999,999 0.07125 <blank> <blank> <blank> <blank>

Example 3:

  • Charge the first 300 kWh per kW of billing demand at 0.0420 per kWh.
  • Charge all remaining consumption at 0.0262 per kWh.

The rows in the grid would be completed as follows:

Through Rate Demand Type Above Multiplier Other Amount
0 0.0420 Demand 0 300 <blank>
999,999,999 0.0262 <blank> <blank> <blank> <blank>